Percentage of Construction Quality Improvement Program (CQIP) specification checkpoints deemed to be in compliance
Measure Last Modified
11-10-2025 03:49 p.m.
Measure Last Published
10-21-2025 02:49 p.m.
Status
Active
Data Source and Calculation
VDOT's Construction Division (CD) collects and analyzes construction project data including compliance with the Construction Quality Improvement Program (CQIP). Effective in 2025 the calculation methodology is as follows: For each contract, it's Total CQIP Score is based only on the criteria within the specification section associated with that contract, and only criteria found to be in non-compliance of that contract are recorded. The CQIP compliance score is calculated as 1 - (number of non-compliance / Total Score) * 100. The Total Score is the equivalence of Total Question Asked in the old CQIP system and Compliant Responses equals to (Total Score - Non-Compliant Responses).
Here is the note on calculation prior to 2025: Construction Division tracks the number of CQIP quality checkpoints found to be in-compliance as a percentage of the total number of checkpoints reviewed for the period, and presents this as the reporting period’s overall CQIP score. VDOT uses CQIP information as part of the overall program of maintaining and improving the quality of construction projects. Values reported here represent year-to-date results that are updated quarterly, which will change as the year progresses.
Updates are typically available from CD mid-month after period end.
Enterprise Priorities and Strategies
Initiative
Priority
Strategy
Transportation
Prioritization
Develop a transparent, data-driven prioritization model to help determine allocations of transportation funding and ensure ongoing accountability
Associated Service Areas
Service Area Code
Service Area Name
60315
Highway Construction Program Management
Targets and Baselines
Name
Date
Result
Note
Baseline
06-30-2018
94.7
Result from fiscal year 2019 based on VDOT Construction Division analysis and reporting.
Short Target 2025
06-30-2025
91.0
Long Target 2027
06-30-2027
91.0
Baseline
None
Results
Year
Result
Note
2019
94.7
Result from fiscal year 2019 based on VDOT Construction Division analysis and reporting.
2020
96.0
Result from fiscal year 2020 based on VDOT Construction Division analysis and reporting. Note: Historical data reflects data as of report run date not 35th day after of end of FY
2021
96.2
Result from fiscal year 2021 based on VDOT Construction Division analysis and reporting. Note: Historical data reflects data as of report run date not 35th day after of end of FY
2022
95.6
Result from fiscal year 2022 based on VDOT Construction Division analysis and reporting. Note: Historical data reflects data as of report run date not 35th day after of end of FY
2023
96.1
Result from fiscal year 2023 based on VDOT Construction Division analysis and reporting. Note: Historical data reflects data as of report run date not 35th day after of end of FY
2024
95.3
Result from fiscal year 2024 based on VDOT Construction Division analysis and reporting.
2025
95.6
Result from fiscal year 2025 based on VDOT Construction Division analysis and reporting.