| Authorize additional funding for nutrient removal programs |
Decision Package |
|
| |
Provides funding to complete support for the Hampton Roads Sanitation District Boat Harbor Treatment Plant project through the Enhanced Nutrient Removal Certainty program. This amendment includes budget language that delineates additional application acceptance requirements for the department. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
$140,555,000 |
$0 |
|
| • |
| Remove one-time funding for Richmond Combined Sewer Overflow |
Decision Package |
|
| |
Corrects base appropriation to account for previously authorized one-time funding. This adjustment is technical in nature. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
($25,000,000) |
($25,000,000) |
|
| • |
| Provide funding for anticipated Stormwater Local Assistance program needs |
Decision Package |
|
| |
Provides funding in the first year to support stormwater assistance projects in localities with municipal separate storm sewer systems. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
$43,494,528 |
$0 |
|
| • |
| Adjust appropriation for centrally funded salary increases for state employees |
Base Budget Adjustment |
|
| |
Adjusts appropriation for the salary increases for state employees budgeted in Central Appropriations, Item 469 R. of Chapter 725, 2025 Acts of Assembly. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
$2,111,156 |
$2,111,156 |
| Nongeneral Fund |
$2,732,383 |
$2,732,383 |
|
| • |
| Conclude support for temporary increase of Virginia Clean Water Revolving Loan Fund match |
Decision Package |
|
| |
Captures general fund support that was previously provided for the department to meet a temporary increase in federal water protection funding. The full commitment is anticipated to be met in the first year of the biennium. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
$0 |
($8,015,880) |
|
| • |
| Align equipment funding with ongoing air and water monitoring needs |
Decision Package |
|
| |
Adjusts base equipment funding for alignment with ongoing needs and anticipated laboratory testing rate increases. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
($1,958,313) |
($1,958,313) |
|
| • |
| Adjust appropriation for centrally funded changes to state health insurance premiums |
Base Budget Adjustment |
|
| |
Adjusts appropriation for the employer’s share of health insurance premiums budgeted in Central Appropriations, Item 469 G. of Chapter 725, 2025 Acts of Assembly. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
$655,556 |
$655,556 |
| Nongeneral Fund |
$848,453 |
$848,453 |
|
| • |
| Adjust appropriation for centrally funded changes to agency information technology costs |
Base Budget Adjustment |
|
| |
Adjusts appropriation for changes to information technology and telecommunications usage budgeted in Central Appropriations, Item 470 C. of Chapter 725, 2025 Acts of Assembly. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
$491,234 |
$491,234 |
| Nongeneral Fund |
$72,495 |
$72,495 |
|
| • |
| Adjust appropriation for centrally funded retirement rate changes |
Base Budget Adjustment |
|
| |
Adjusts appropriation for changes to contribution rates for state employee retirement plans budgeted in Central Appropriations, Item 469 H. of Chapter 725, 2025 Acts of Assembly. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
($186,169) |
($186,169) |
| Nongeneral Fund |
($240,949) |
($240,949) |
|
| • |
| Adjust appropriation for centrally funded other post-employment benefit rate changes |
Base Budget Adjustment |
|
| |
Adjusts appropriation for changes to state employee other post-employment benefit rates budgeted in Central Appropriations, Item 469 J. of Chapter 725, 2025 Acts of Assembly. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
($72,579) |
($72,579) |
| Nongeneral Fund |
($93,934) |
($93,934) |
|
| • |
| Adjust appropriation for centrally funded changes to Cardinal Financials System charges |
Base Budget Adjustment |
|
| |
Adjusts appropriation for changes to Cardinal Financials System internal service fund charges budgeted in Central Appropriations, Item 470 E. of Chapter 725, 2025 Acts of Assembly. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
($13,537) |
($13,537) |
| Nongeneral Fund |
($68,485) |
($68,485) |
|
| • |
| Adjust appropriation for centrally funded workers’ compensation premium changes |
Base Budget Adjustment |
|
| |
Adjusts appropriation for workers’ compensation premiums budgeted in Central Appropriations, Item 469 O. of Chapter 725, 2025 Acts of Assembly. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
($21,884) |
($21,884) |
| Nongeneral Fund |
($56,646) |
($56,646) |
|
| • |
| Adjust appropriation for centrally funded liability insurance premium charges |
Base Budget Adjustment |
|
| |
Adjusts appropriation for liability insurance premiums billed by the Department of the Treasury’s Division of Risk Management budgeted in Central Appropriations, Item 470 J. of Chapter 725, 2025 Acts of Assembly. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
$71,000 |
$71,000 |
| Nongeneral Fund |
$1,034 |
$1,034 |
|
| • |
| Adjust appropriation for centrally funded changes to agency leased space costs |
Base Budget Adjustment |
|
| |
Adjusts appropriation for reduced charges to customer agencies for the Department of General Services to perform lease administration services budgeted in Central Appropriations, Item 470 I. of Chapter 725, 2025 Acts of Assembly. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
($8,730) |
($8,730) |
| Nongeneral Fund |
($40,622) |
($40,622) |
|
| • |
| Adjust appropriation for centrally funded changes to Cardinal Human Capital Management System charges |
Base Budget Adjustment |
|
| |
Adjusts appropriation for changes to Cardinal Human Capital Management System internal service fund charges budgeted in Central Appropriations, Item 470 F. of Chapter 725, 2025 Acts of Assembly.
|
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
$1,441 |
$1,441 |
| Nongeneral Fund |
($25,291) |
($25,291) |
|
| • |
| Adjust appropriation for centrally funded property insurance premium charges |
Base Budget Adjustment |
|
| |
Adjusts appropriation for property insurance premiums billed by the Department of the Treasury’s Division of Risk Management budgeted in Central Appropriations, Item 470 M. of Chapter 725, 2025 Acts of Assembly. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
$12,248 |
$12,248 |
|
| • |
| Adjust appropriation for centrally funded changes to agency vehicle fleet charges |
Base Budget Adjustment |
|
| |
Adjusts appropriation for reduced fleet vehicle operational rate charges billed by the Department of General Services budgeted in Central Appropriations, Item 470 H. of Chapter 725, 2025 Acts of Assembly. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
($7,578) |
($7,578) |
| Nongeneral Fund |
($4,339) |
($4,339) |
|
| • |
| Cover the cost of Ohio River Valley Water Sanitation Commission fee increase |
Decision Package |
|
| |
Provides general fund support for increased Ohio River Valley Water Sanitation Commission membership dues. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
$2,640 |
$4,264 |
|
| • |
| Adjust appropriation for centrally funded changes to Performance Budgeting system charges |
Base Budget Adjustment |
|
| |
Adjusts appropriation for changes to Performance Budgeting system internal service fund charges budgeted in Central Appropriations, Item 470 G. of Chapter 725, 2025 Acts of Assembly. |
| |
| |
FY 2027 |
FY 2028 |
| General Fund |
$438 |
$438 |
| Nongeneral Fund |
$194 |
$194 |
|
| • |
| Reallocate appropriation to the correct service area |
Decision Package |
|
| |
Moves appropriation for proper accounting and adjusts the allotment of matching funds provided for a temporary increase in the Virginia Clean Water Revolving Loan Fund. |