The 2025 Executive Budget Document
Governor Youngkin's Proposed Amendments to the 2024-2026 Biennial Budget
 Back to Front Page
Released on December 18, 2025 
 
Central Capital Outlay [949]
Secretarial Area: Central Appropriations
Operating Budget Summary
This table shows the Governor's proposed budget for the next two years and the agency's official budget for the previous six years.
more...
Biennium Fiscal Year Source GF NGF Total
Positions Budget Summary
Biennium Fiscal Year Source GF NGF Total
Operating Budget Addenda (in order of greatest impact)
None for this agency
Capital Project Requests (in order of largest to smallest)
Supplant bonds with general fund for the Water Quality Improvement Fund
  Supplants the $400 million existing bond authorization for Water Quality Improvement Fund eligible wastewater projects with general fund from FY 2024 revenues in excess of the official revenue estimate, pursuant to Item 470 K.2. of Chapter 2, 2024 Acts of Assembly, Special Session I. All general fund appropriation is provided in FY 2025.
 
  FY 2025 FY 2026
General Fund $400,000,000 $0
Tax Supported Debt ($200,000,000) ($200,000,000)
2025 Higher Ed Construction Pool
  Provides funding for the construction and acquisition of eight capital projects at institutions of higher education. Funding for multiple projects is pooled together centrally and subject to the capital pool process in Section 2.2-1515 et. seq, Code of Virginia.
 
  FY 2025 FY 2026
General Fund $448,214,251 $0
Nongeneral Fund $80,331,520 $0
Adjust 2022 construction pool for State Police Training Academy
  Adjusts funding and project authorization in the 2022 state agency construction pool, which pools funding for capital projects together centrally.
 
  FY 2025 FY 2026
General Fund $136,311,497 $0
2025 Non Higher Ed Construction Pool
  Provides funding for the construction and acquisition of eight capital projects for state agencies. Funding for multiple projects is pooled together centrally and subject to the capital pool process in Section 2.2-1515 et. seq, Code of Virginia. This pool includes projects for agencies other than institutions of higher education.
 
  FY 2025 FY 2026
General Fund $130,451,057 $0
Adjustment to Statewide Supplement Pool
  Adjusts funding for the central statewide supplement pool and updates eligibility criteria for use of supplement pool funding.
 
  FY 2025 FY 2026
General Fund $62,362,850 $0
Planning Pool
  Authorizes detailed planning for six capital projects and preplanning for one project in a central planning pool. The scope for one project previously authorized in the planning pool is also adjusted.
 
  FY 2025 FY 2026
General Fund $31,948,103 $0
Nongeneral Fund $9,130,897 $0
Adjust 2020 Higher Ed Construction Pool for VCCS Godwin Building Scope Change
  Adjusts the scope of the Virginia Community College System Godwin Building project in the Annandale Campus in Northern Virginia from a renovation to a replacement and adjusts funding in the 2020 VCBA construction pool in which the project is authorized.
 
  FY 2025 FY 2026
General Fund $15,545,100 $0
Placeholder: Equipment pool
  Provides funding to be disbursed to agencies and institutions of higher education for equipment purchases related to previously authorized capital projects.
 
  FY 2025 FY 2026
General Fund $14,511,505 $0
Remove requirement for Six-Year Capital Outlay Plan Advisory Committee to make recommendations about capital budget requests
  Provides language in Section 2-0 to remove a requirement for the Six-Year Capital Outlay Plan Advisory Committee to make recommendations about capital budget requests.
Lease and Financed Purchase Authorizations
  Provides language authorizing numerous lease and financed purchase agreements.
Redirect balances from completed and cancelled projects
  Redirects balances from completed standalone projects and projects that agencies no longer wish to execute to construction pools that are not expected to have sufficient funding.
Clarify Crewe Water Project Scope and Authorize use of Supplement Pool
  Provides budget language to clarify the intended scope of the Nottoway water infrastructure project and authorizes the use of funding from the statewide supplement pool for any project costs in excess of those originally assumed when the project was authorized in the 2020 construction pool.
Adjust project scope in 2024 State Agency Capital Account construction pool
  Provides authority for previously authorized funds to be used for temporary heat and hot water solutions at Hiram Davis Medical Center pending final disposition of the facility.


pdocagy2014 - Executive Budget Document Agency Details - 06-02-2025 08:32:00