This table shows the Governor's proposed budget for the next two years and the agency's official budget for the previous six years. more...
More historical data is available for this agency on DPB's website under the
Virginia's Budget page. If you click on the Budget Round Description links under any of the "DPB Appropriation Database" tables and open the filter you can select various fields to get greater detail and you can select the official chapter data going back for several decades. The "Caboose" chapters are the final biennial budget approved by the General Assembly and signed into Law.
Check it out here
Biennium
Fiscal Year
Source
GF
NGF
Total
2020-2022
2021
Chapter 1, 2022 Acts of Assembly
$0
$315,532,483
$315,532,483
2021-2024
2022
Chapter1, 2024 Acts of Assembly
$0
$324,011,106
$324,011,106
2020-2022
2022
Chapter 1, 2022 Acts of Assembly
$0
$319,532,483
$319,532,483
2021-2024
2023
Chapter1, 2024 Acts of Assembly
$0
$323,616,656
$323,616,656
2024-2026
2025
Governor's Proposed Budget
$0
$342,735,328
$342,735,328
2024 Appropriation
$0
$342,735,328
$342,735,328
Governor's Amendments
$0
$0
$0
2024-2026
2026
Governor's Proposed Budget
$0
$367,735,328
$367,735,328
2024 Appropriation
$0
$342,735,328
$342,735,328
Governor's Amendments
$0
$25,000,000
$25,000,000
Positions Budget Summary
Biennium
Fiscal Year
Source
GF
NGF
Total
2020-2022
2021
Chapter 1, 2022 Acts of Assembly
0.00
2,222.00
2,222.00
2021-2024
2022
Chapter1, 2024 Acts of Assembly
0.00
2,225.00
2,225.00
2020-2022
2022
Chapter 1, 2022 Acts of Assembly
0.00
2,222.00
2,222.00
2021-2024
2023
Chapter1, 2024 Acts of Assembly
0.00
2,225.00
2,225.00
2024-2026
2025
Proposed Positions
0.00
2,225.00
2,225.00
2024 Appropriation
0.00
2,225.00
2,225.00
Governor's Amendments
0.00
0.00
0.00
2024-2026
2026
Proposed Positions
0.00
2,225.00
2,225.00
2024 Appropriation
0.00
2,225.00
2,225.00
Governor's Amendments
0.00
0.00
0.00
Operating Budget Addenda (in order of greatest impact)
•
Support mainframe replacement project
Decision Package
Provides nongeneral fund appropriation to support costs of modernizing the agency's mainframe system and transitioning to a modern server-based system.
FY 2025
FY 2026
Nongeneral Fund
$0
$25,000,000
•
Align appropriation with anticipated spending
Decision Package
Adjusts nongeneral fund appropriation to align with the agency's current financial plan.
•
Authorize credit card convenience fee for transactions $10,000 and over
Decision Package
Authorizes the Department of Motor Vehicles to charge a 1.5 percent convenience fee for credit card transactions $10,000 and over.
•
Retain rental revenue
Decision Package
Authorizes the Department of Motor Vehicles to retain the income generated by the rental of space in agency-owned facilities.
Capital Project Requests (in order of largest to smallest)
•
Renovate DMV Headquarters
Fund the next phase of the previously approved project to renovate the Department of Motor Vehicles headquarters.
FY 2025
FY 2026
Nongeneral Fund
$0
$16,000,000
•
Fund maintenance reserve
Adds additional nongeneral funds to existing maintenance reserve project for costs associated with continuing maintenance needs.