| Remove one-time deposit deposit into the Stormwater Local Assistance Fund |
Base Budget Adjustment |
|
| |
Removes $25 million deposit into the Stormwater Local Assistance Fund. |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
($25,000,000) |
($25,000,000) |
|
| • |
| Meet anticipated increase in Virginia Clean Water Revolving Loan Fund match |
Decision Package |
|
| |
Provides general fund support for the agency to meet matching requirements corresponding to anticipated federal funding available through the Virginia Clean Water Revolving Loan Fund as a result of the Infrastructure Investment and Jobs Act |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
$8,125,920 |
$9,515,880 |
|
| • |
| Establish appropriation for administration of the Regional Greenhouse Gas Initiative (RGGI) participation and climate change planning and mitigation activities |
Base Budget Adjustment |
|
| |
Builds in base appropriation for DEQ's administration of the Commonwealth's participation in RGGI, and for the agency's utilization of a portion of the proceeds in climate change planning and mitigation activities, as established in the Clean Energy and Community Flood Preparedness Act. |
| |
| |
FY 2023 |
FY 2024 |
| Nongeneral Fund |
$5,600,000 |
$5,600,000 |
|
| • |
| Adjust appropriation for centrally funded five percent salary increase for state employees |
Base Budget Adjustment |
|
| |
Adjusts appropriation for the five percent salary increase for state employees budgeted in Central Appropriations, Item 477 X. of Chapter 552, 2021 Acts of Assembly, Special Session I. |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
$1,285,147 |
$1,285,147 |
| Nongeneral Fund |
$2,002,295 |
$2,002,295 |
|
| • |
| Support multiple separate storm sewer system permit obligations in Town of Dumfries |
Decision Package |
|
| |
Funds activities to comply with permitting requirements in the Town of Dumfries |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
$3,000,000 |
$0 |
|
| • |
| Adjust appropriation for centrally funded changes to agency information technology costs |
Base Budget Adjustment |
|
| |
Adjusts appropriation for changes to information technology and telecommunications usage budgeted in Central Appropriations, Item 478 C. of Chapter 552, 2021 Acts of Assembly, Special Session I. |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
($1,079,437) |
($1,079,437) |
| Nongeneral Fund |
($409,826) |
($409,826) |
|
| • |
| Adjust appropriation for centrally funded retirement rate changes |
Base Budget Adjustment |
|
| |
Adjusts appropriation for changes to contribution rates for state employee retirement plans budgeted in Central Appropriations, Item 477 H. of Chapter 552, 2021 Acts of Assembly, Special Session I. |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
$193,083 |
$193,083 |
| Nongeneral Fund |
$300,833 |
$300,833 |
|
| • |
| Provide funding for agency ombudsmen positions |
Decision Package |
|
| |
Provides general fund support for three ombudsmen positions |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
$366,300 |
$366,300 |
|
| • |
| Adjust appropriation for centrally funded changes to state health insurance premiums |
Base Budget Adjustment |
|
| |
Adjusts appropriation for the employer’s share of health insurance premiums budgeted in Central Appropriations, Item 477 G. of Chapter 552, 2021 Acts of Assembly, Special Session I. |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
$128,402 |
$128,402 |
| Nongeneral Fund |
$195,002 |
$195,002 |
|
| • |
| Support erosion and sediment control permitting for solar projects |
Decision Package |
|
| |
Provides funding for two positions for solar permitting |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
$250,000 |
$250,000 |
|
| • |
| Adjust appropriation for centrally funded workers’ compensation premium changes |
Base Budget Adjustment |
|
| |
Adjusts appropriation for workers’ compensation premiums budgeted in Central Appropriations, Item 477 R. of Chapter 552, 2021 Acts of Assembly, Special Session I. |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
$42,896 |
$42,896 |
| Nongeneral Fund |
$133,619 |
$133,619 |
|
| • |
| Remove one-time funding for salt reduction research project. |
Base Budget Adjustment |
|
| |
Removes $175,000 the second year for a field test of using native plants to capture and remove salt from paved surface stormwater runoff. |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
($175,000) |
($175,000) |
|
| • |
| Adjust appropriation for centrally funded changes to Cardinal Human Capital Management System charges |
Base Budget Adjustment |
|
| |
Adjusts appropriation for changes to Cardinal Human Capital Management System internal service fund charges budgeted in Central Appropriations, Item 478 G. of Chapter 552, 2021 Acts of Assembly, Special Session I. |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
$65,672 |
$65,672 |
| Nongeneral Fund |
$102,282 |
$102,282 |
|
| • |
| Support stormwater activities in the Town of Occoquan |
Decision Package |
|
| |
Provides funding for the Town of Occoquan to carry out stormwater dredging activities |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
$325,000 |
$0 |
|
| • |
| Increase administrative capacity in water quality programs |
Decision Package |
|
| |
Provides general fund support for the addition of one administrative position for the agency's stormwater local assistance and nutrient reduction grant programs |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
$122,100 |
$122,100 |
|
| • |
| Adjust appropriation for centrally funded general liability premium charges |
Base Budget Adjustment |
|
| |
Adjusts appropriation for general liability premiums billed by the Department of the Treasury’s Division of Risk Management budgeted in Central Appropriations, Item 478 J. of Chapter 552, 2021 Acts of Assembly, Special Session I. |
| |
| |
FY 2023 |
FY 2024 |
| Nongeneral Fund |
$26,764 |
$26,764 |
|
| • |
| Adjust appropriation for centrally funded changes to Cardinal Financials System charges |
Base Budget Adjustment |
|
| |
Adjusts appropriation for changes to Cardinal Financials System internal service fund charges budgeted in Central Appropriations, Item 478 F. of Chapter 552, 2021 Acts of Assembly, Special Session I. |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
($5,577) |
($5,577) |
| Nongeneral Fund |
($20,709) |
($20,709) |
|
| • |
| Adjust appropriation for centrally funded internal service fund charges for the Personnel Management Information System |
Base Budget Adjustment |
|
| |
Adjusts appropriation for Personnel Management Information System internal service fund charges budgeted in Central Appropriations, Item 478 I. of Chapter 552, 2021 Acts of Assembly, Special Session I. |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
($2,927) |
($2,927) |
| Nongeneral Fund |
($2,598) |
($2,598) |
|
| • |
| Adjust appropriation for centrally funded state employee other post-employment benefit rate changes |
Base Budget Adjustment |
|
| |
Adjusts appropriation for changes to state employee other post-employment benefit rates budgeted in Central Appropriations, Item 477 K. of Chapter 552, 2021 Acts of Assembly, Special Session I. |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
$2,055 |
$2,055 |
| Nongeneral Fund |
$3,203 |
$3,203 |
|
| • |
| Adjust appropriation for centrally funded changes to Performance Budgeting system charges |
Base Budget Adjustment |
|
| |
Adjusts appropriation for changes to Performance Budgeting system internal service fund charges budgeted in Central Appropriations, Item 478 H. of Chapter 552, 2021 Acts of Assembly, Special Session I. |
| |
| |
FY 2023 |
FY 2024 |
| General Fund |
($344) |
($344) |
| Nongeneral Fund |
($1,338) |
($1,338) |
|
| • |
| Administer the Regional Greenhouse Gas Initiative program |
Decision Package |
|
| |
Transfers positions within the agency to meet workload increases related to the adminsitration of the Commonwealth's participation in the Regional Greenhouse Gas Initiative |