The 2020 Executive Budget Document
Governor Northam's Proposed Budget for the 2020-2022 Biennum
 Back to Front Page
Released on December 17, 2019 
 
Central Capital Outlay [949]
Secretarial Area: Central Appropriations
Operating Budget Summary
This table shows the Governor's proposed budget for the next two years and the agency's official budget for the previous six years.
more...
Biennium Fiscal Year Source GF NGF Total
Positions Budget Summary
Biennium Fiscal Year Source GF NGF Total
Operating Budget Addenda (in order of greatest impact)
None for this agency
Capital Project Requests (in order of largest to smallest)
2020 VCBA Capital Construction Pool
  Provides funding for the construction of a variety of capital projects at institutions of higher education.
 
  FY 2021 FY 2022
Tax Supported Debt $780,461,508 $0
Local Water Quality and Supply Projects
  Provides funding for the Stormwater Local Assistance Fund, Nutrient Removal Grants, and the Combined Sewer Overflow Matching Fund. Funding for the Combined Sewer Overflow Matching Fund is authorized to pay a portion of the capital costs of the City of Alexandria' combined sewer overflow control project.
 
  FY 2021 FY 2022
Tax Supported Debt $367,000,000 $0
2020 VPBA Capital Construction Pool
  Provides funding for the construction of a variety of capital projects for agencies. This pool includes projects for agencies other than institutions of higher education.
 
  FY 2021 FY 2022
Nongeneral Fund $91,449,317 $0
Tax Supported Debt $218,808,753 $0
Central Maintenance Reserve
  Provides funding to be distributed to agencies and institutions of higher education to address critical maintenance needs in state-owned facilities. This funding can be used to address major repairs or replacements that are intended to extend the useful life of the physical plant, property, and equipment.
 
  FY 2021 FY 2022
Nongeneral Fund $130,000,000 $130,000,000
Supplement Previously Authorized Capital Project Construction Pools
  Provides funding available to be transferred between and among other capital construction pools in order to address any shortfall in appropriation in other capital pools.
 
  FY 2021 FY 2022
Nongeneral Fund $145,700,000 $0
Central Reserve for Capital Equipment Funding
  Provides bond authorization to be disbursed to agencies and institutions of higher education for equipment purchases related to previously authorized capital projects.
 
  FY 2021 FY 2022
Tax Supported Debt $93,063,337 $0
Other Authorized Capital Infrastructure and Improvements
  Contributes toward the construction of additional hospital beds at the Children's Hospital of the King's Daughters and provides funding for a potential infrastructure improvement project at the Portsmouth Marine Terminal.
 
  FY 2021 FY 2022
Tax Supported Debt $73,400,000 $0
Workforce Development Projects
  Provides funding to support capital investment associated with bolstering technology-related education to address workforce needs.
 
  FY 2021 FY 2022
Tax Supported Debt $13,600,000 $8,500,000
Detail Planning for Capital Projects
  Provides funding to support pre-planning and detailed planning for a variety of capital projects.
 
  FY 2021 FY 2022
General Fund $16,956,290 $0