Open work item in PB work tray
Improve Readiness Centers
Department of Military Affairs (123)
Request Title Provide additional general funds for readiness center improvement projects
Project Code 18369
Project Type Improvements-Infrastructure Repairs
Biennium 2026-2028
Budget Round Initial Bill
Facility Department of Military Affairs
Source Capital Budget Request
Infrastructure Element 8
Budget Bullet

Supplements an existing umbrella capital project to fund improvements at the Bedford Readiness Center.

Project Funding
Fund Type FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
GF $2,800,000 $0 $0 $0 $0 $0
NGF $0 $0 $0 $0 $0 $0
9C Debt $0 $0 $0 $0 $0 $0
9D Debt $0 $0 $0 $0 $0 $0
Tax Supported Debt $0 $0 $0 $0 $0 $0
Total $2,800,000 $0 $0 $0 $0 $0