Radford University (217)
Request Title | Install Combined Heating and Power Cogeneration Facility |
Project Code | 18598 |
Project Type | Improvements-Energy Efficiency |
Biennium | 2022-2024 |
Budget Round | Initial Bill |
Facility | Radford University |
Source | Capital Budget Request |
Infrastructure Element | 43 |
Budget Bullet
Installs two 3.3 MW natural gas fired reciprocating engines, resulting in significantly reducing the university's current electrical expenses by as much as $2 million annually, while reducing its carbon footprint. |
Project Funding
Fund Type | FY 2022 | FY 2023 | FY 2024 | FY 2025 | FY 2026 | FY 2027 |
GF | $11,200,000 | $0 | $0 | $0 | $0 | $0 |
NGF | $4,800,000 | $0 | $0 | $0 | $0 | $0 |
9C Debt | $0 | $0 | $0 | $0 | $0 | $0 |
9D Debt | $0 | $0 | $0 | $0 | $0 | $0 |
Tax Supported Debt | $0 | $0 | $0 | $0 | $0 | $0 |
Total | $16,000,000 | $0 | $0 | $0 | $0 | $0 |