The College of William and Mary in Virginia (204)
Request Title | Renovate: Kaplan Arena & Construct: Sports Performance Center |
Project Code | 18467 |
Project Type | New Construction/Improvement |
Biennium | 2020-2022 |
Budget Round | Initial Bill |
Facility | Main Campus |
Source | Capital Budget Request |
Infrastructure Element | 9 |
Budget Bullet
Addresses critical issues such as replacement of aging mechanical, electric, plumbing and fire protection systems, removal of asbestos-containing materials, and overall modernization (energy efficient fixtures, modern scoreboard, and updated telecommunications abilities). |
Project Funding
Fund Type | FY 2020 | FY 2021 | FY 2022 | FY 2023 | FY 2024 | FY 2025 |
GF | $0 | $0 | $0 | $0 | $0 | $0 |
NGF | $0 | $0 | $0 | $0 | $0 | $0 |
9C Debt | $0 | $0 | $0 | $0 | $0 | $0 |
9D Debt | $55,000,000 | $0 | $0 | $0 | $0 | $0 |
Tax Supported Debt | $0 | $0 | $0 | $0 | $0 | $0 |
Total | $55,000,000 | $0 | $0 | $0 | $0 | $0 |