Christopher Newport University (242)
| Request Title | Integrated Science Center, Phase III |
| Project Code | 18496 |
| Project Type | New Construction |
| Biennium | 2020-2022 |
| Budget Round | Caboose Bill |
| Facility | Christopher Newport University |
| Source | Capital Budget Request |
| Infrastructure Element | 22 |
Budget Bullet
|
Provides state funding for detailed planning of the third phase of the Integrated Science Center, which was previously authorized for detailed planning with nongeneral funds in Chapter 1289, 2020 Acts of Assembly. |
Project Funding
| Fund Type | FY 2020 | FY 2021 | FY 2022 | FY 2023 | FY 2024 | FY 2025 |
| GF | $0 | $2,061,000 | $0 | $0 | $0 | $0 |
| NGF | $0 | $0 | $0 | $0 | $0 | $0 |
| 9C Debt | $0 | $0 | $0 | $0 | $0 | $0 |
| 9D Debt | $0 | $0 | $0 | $0 | $0 | $0 |
| Tax Supported Debt | $0 | $0 | $0 | $0 | $0 | $0 |
| Total | $0 | $2,061,000 | $0 | $0 | $0 | $0 |