Department of Corrections (799)
Request Title | Authorize expansion of Goochland-VCCW wastewater treatment plant |
Project Code | 18532 |
Project Type | Improvements-Other |
Biennium | 2020-2022 |
Budget Round | Amended Bill |
Facility | Virginia Correctional Center for Women |
Source | Capital Budget Request |
Infrastructure Element | 145 |
Budget Bullet
Establishes a nongeneral fund supported project to expand the wastewater treatment plant to accommodate additional capacity needed by Goochland County. Per an agreement between the county and the Department of Corrections (DOC), DOC will manage the construction project and the county will pay all construction costs. |
Project Funding
Fund Type | FY 2020 | FY 2021 | FY 2022 | FY 2023 | FY 2024 | FY 2025 |
GF | $0 | $0 | $0 | $0 | $0 | $0 |
NGF | $198,717 | $3,000,000 | $0 | $0 | $0 | $0 |
9C Debt | $0 | $0 | $0 | $0 | $0 | $0 |
9D Debt | $0 | $0 | $0 | $0 | $0 | $0 |
Tax Supported Debt | $0 | $0 | $0 | $0 | $0 | $0 |
Total | $198,717 | $3,000,000 | $0 | $0 | $0 | $0 |