Open work item in PB work tray
Authorize expansion of Goochland-VCCW wastewater treatment plant
Department of Corrections (799)
Request Title Authorize expansion of Goochland-VCCW wastewater treatment plant
Project Code 18532
Project Type Improvements-Other
Biennium 2020-2022
Budget Round Amended Bill
Facility Virginia Correctional Center for Women
Source Capital Budget Request
Infrastructure Element 145
Budget Bullet

Establishes a nongeneral fund supported project to expand the wastewater treatment plant to accommodate additional capacity needed by Goochland County. Per an agreement between the county and the Department of Corrections (DOC), DOC will manage the construction project and the county will pay all construction costs.

Project Funding
Fund Type FY 2020 FY 2021 FY 2022 FY 2023 FY 2024 FY 2025
GF $0 $0 $0 $0 $0 $0
NGF $198,717 $3,000,000 $0 $0 $0 $0
9C Debt $0 $0 $0 $0 $0 $0
9D Debt $0 $0 $0 $0 $0 $0
Tax Supported Debt $0 $0 $0 $0 $0 $0
Total $198,717 $3,000,000 $0 $0 $0 $0