Supplemental funding: Capitol Complex Infrastructure and Security (Project 18081)
Central Capital Outlay (949)
Request Title Supplement Capitol Square Infrastructure Project
Project Code 18382
Project Type None
Biennium 2018-2020
Budget Round Initial Bill
Facility NULL
Source General Assembly Adjustment
Infrastructure Element NULL
Budget Bullet

This amendment provides a supplement to account for price escalation. In addition, language provides for the necessary easements to execute the project.

Project Funding
Fund Type FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023
GF $0 $0 $0 $0 $0 $0
NGF $11,820,000 $0 $0 $0 $0 $0
9C Debt $0 $0 $0 $0 $0 $0
9D Debt $0 $0 $0 $0 $0 $0
Tax Supported Debt $0 $0 $0 $0 $0 $0
Total $11,820,000 $0 $0 $0 $0 $0


p3_capview - Official Enacted Budget View Operating Bullet Details - 06-06-2025 13:06:53